+44 207 488 9947
The case of Spiersbridge Property Developments Ltd v Muir Construction Ltd [2008] involved a determination relating to an action alleging breach of a building contract. A bank had paid out an amount demanded by the pursuer under a performance bond and it had to be decided, if the demand on the bond exceeded the sum ultimately due, whether the pursuer was obliged to account for the excess to the bank or to the defender.
The pursuer in this case was a property development company and the defender was a construction company. The parties entered into a building contract in June 2005, in accordance with this contract, the defender was to design and construct a development consisting of warehouses and office space.
This case was centred on the pursuer claiming for alleged delays in completing the works whilst the defender counterclaimed, requesting for an extension of time in which it could complete its obligations.
According to clause 2.10.2 of Appendix 1 of the building contract, the defender, as the contractor, made an undertaking to execute and deliver to the pursuer, as the employer, no later than 14 days following a written request from the pursuer to do so:
“…A performance bond in an amount not less than 10% of the Contract Sum in terms the same as the draft performance bond set out in Part Five of this Schedule”.
The Bank of Scotland subsequently issued a performance bond. The performance bond was in the form of a letter which was addressed to the pursuers and included substantially the same terms as the draft bond referred to in clause 2.10.2.
Then, in November 2006, the pursuer made a demand requiring the bank to pay £503,193.75 under the bond, which the bank duly paid to the pursuer. The defender stated that it was obliged, under a counter-indemnity it had granted to the bank, to pay that same amount to the bank and that it had duly done so.
Furthermore, the defender stated in its counterclaim that the grounds on which the pursuer called on the bond were erroneous. The defender argued that the grounds were erroneous due to the fact that it was not in breach of contract as alleged by the pursuer. It asserted that the pursuer was obliged to account to it for the sums received under the bond. The basis for that assertion being that the following term was to be implied into the building contract:
“…In the event that… the pursuer should make a call on the bond it would account to the defender for the proceeds of the bond, retaining only the amount equivalent to any loss suffered by the pursuer as a result of the defender's breach of contract, if any”.
It was argued that such a term required to be implied as a matter of business efficacy. This meant that the dispute as to whether the defender was in breach of the building contract, as alleged by the pursuer, was yet to be settled.
Despite the fact that a ‘proof before answer’ had been appointed, the parties also disagreed on whether the pursuer was obliged to account to the defender for that excess, assuming it was found to be entitled to a sum less than it was paid under the bond.
Accordingly, the pursuer argued that its duty to account was owed to the bank and not to the defender. The pursuer’s principal concern was that if it made payment of that excess to the defender, it risked being sued for an equal sum by the bank.
The parties came to the mutual decision to have the issue decided in a debate before the proof. The question for decision during the debate was:
“Where a demand had been made on a performance bond in an amount which was ultimately found to exceed the sum due to the party making the demand, was that party obliged to account for that excess:
(a) To the bank; or
(b) To his opposite contracting party?”
Counsel for the pursuer said that there were three contracts which needed to be considered:
§ The bond contract, namely the contract on the performance bond between the pursuer and the bank;
§ The building contract, which was the contract between the pursuer and the defender; and
§ The banking contract between the defender and the bank pursuant to which the bank agreed to issue the performance bond.
It had to be decided to whom the pursuer should account for the excess and the route to achieve this. It was submitted that the most sensible route was by implication of a term into the bond contract. The term would state that the pursuer would repay the excess to the bank. This would be matched by a corresponding term to be implied into the banking contract under which, if it had already been paid by the defender, the bank would repay the said amount to the defender.
This however raised some potential difficulties. If the term was implied into the building contract where the defender became insolvent, and the pursuer was required to account for the excess to the defender, the payment by the pursuer would go into the pot for the general body of creditors of the defender. This would mean that unless it had already been paid by the defender, the bank would lose out.
Counsel for the defender submitted that the term should be implied in the building contract. If it were the case that it was the bank that could sue on the bond for the excess, the bank would be undertaking the burden of seeking to prove in litigation with the pursuer that the defender was not in breach of contract. Alternatively, that the damage suffered by the pursuer was less than the amount called under the bond.
It was argued that that was not a task a reasonable banker would be particularly willing to undertake, not just because of the difficulty of running such a case, but also due to the fact that it would be expensive.
It would be much better for the bank to be able to rely upon its counter-indemnity from the defender at the time that the bond was called. If the bank had the right of action for recovery of the excess, counsel for the pursuer argued that those difficulties could be overcome by an assignment of the right of action by the bank to the defender. However, this would not work as the terms of the bond prohibited the bank from assigning its rights without the pursuer's consent. Furthermore, if the bank had been paid by the defender pursuant to its counter-indemnity, it would not have suffered any loss and would have no claim to assign.
After much deliberation, the court held that where a demand was made on a performance bond in an amount which was ultimately found to exceed the sum due to the party making the demand, that party was held to be obliged to account for that excess to the opposite contracting party. In the circumstances of this case, the parties had agreed that the obligation on the pursuer to account for any excess must rest upon an implied term in one of the contracts to which it was a party.
This meant that the question then became one of establishing which implication best gave the intended business efficacy to the transaction.
The court was of the opinion that the natural implication was an implication of the type for which the defender argued, namely an implication of a term into the building contract as follows:
'…In the event that… the pursuer should make a call on the bond it would account to the defender for the proceeds of the bond, retaining only the amount equivalent to any loss suffered by the pursuer as a result of the defender's breach of contract, if any'.
It was held that a term implied into the building contract had none of the disadvantages of involving the bank in the merits of the case. Furthermore, it also allowed for establishing what loss, if any, the pursuer had suffered as a result of the defender's alleged breach of the building contract. This could be determined in litigation or arbitration between the parties to that contract.
The court further held that it was unrealistic to think that the bank would not have agreed with the defender a counter-indemnity in terms of which the defender would in turn indemnify the bank in the like amount upon a call being made upon the bond.
In the event that the call on the bond was excessive, the defender would be out of pocket, not the bank. According to the court, it seemed quite natural that it should be the defender to whom the pursuer had to account for that excess. This did however leave one potential problem. That problem being that if the defender became insolvent after the bond was established by the bank, but before the bank could claim against the defender on the counter-indemnity, then the bank would stand to lose out if it had not taken security.
This potential problem was held to merely be a commercial risk which the bank would decide whether or not to take depending upon its assessment of the defender's creditworthiness. As such, the bank could overcome this problem by refusing to issue the bond, or require some security before agreeing to issue it.
Please contact us for more information at [email protected]
Visit http://www.rtcoopers.com/practice_corporatecommercial.php
© RT COOPERS, 2008. This Briefing Note does not provide a comprehensive or complete statement of the law relating to the issues discussed nor does it constitute legal advice. It is intended only to highlight general issues. Specialist legal advice should always be sought in relation to particular circumstances.